Central College Data Center

 

Data Center and ITS Relocation
Central College, Pella, Iowa

Central College had outgrown its data center and needed more space for its IT Staff.   Tim Olson was hired to provide a design solution that would repurpose a space previously used as a physical plant and maintenance shop.  The design solution provided office space for 14 IT staff and a 540 SF raised floor space for data racks with overhead bus and underfloor cooling.

Completion Date: 2010

Cost: $1.5M

Project Team:

  • Tim Olson, AIA, NCARB LEED AP: Principal-in-Charge / Project Manager / Project Architect with SVPA
  • MEP Associates
  • The Weitz Company with the Owner.

Project Type:  Data Center  -  Higher Education