North Polk Schools has two elementary schools, one in Polk City and one in Alleman.  Both schools were built in 1980, and Tim Olson was hired to design additions to both schools in 2000.  In 2012, Tim was hired again to provide design services and construction administration for re-roofing the original buildings at both campuses.   The High School Gym was also in dire need of a new roof.

Completion Date:  2012

Project Cost: $393,567

  • Elementary Schools: $325,78
  • High School Gym: $67,787

Per Project Size: 25,000 SF +/-

Project Team:

  • Tim Olson, AIA, NCARB, LEED AP: Principal-in-Charge / Project Manager / Project Architect with previous employers

Project Type:  K-12  -  Roofing/Building Envelope