Principal Data Center Expansion

 

Principal Data Center Expansion
Johnston, Iowa

Principal Financial Group needed a 9,750 SF addition Live Upgrade to an existing Data Center done in three phases.  (1) Electrical Room: provided redundancy with all Electrical Systems, (2) Loading Dock Expansion: Provided clean room and new loading dock with more efficient dock equipment, and (3) Security Addition / new entry.

Completion Date:  June 2012

Project Size:   9,750 SF

Cost:  $12.8M

Project Team:

  • Tim Olson: Project Manager / Project Architect with RDG

  • Ryan Companies

  • Baker Group

  • Baker Electric

  • Saul Engineering

  • Bishop Engineering

Project Type:  CorporateData Center